Photo report on the progress of construction of the enterprise LLC RusSilika on the territory of the SEZ Kulibin (Dzerzhinsk, Nizhny Novgorod region). December 2024.
The main technological equipment manufactured by European companies continues to arrive at the construction site of the RusSilika LLC plant. The equipment is installed, as they say, on the fly. ARCO® Company carries out weekly supervision of the construction of production facilities and infrastructure facilities within the framework of the General Designer's Author's Supervision. During the construction process and constant selection of equipment and systems, it becomes necessary to make new technical and design decisions and promptly make changes to the working documentation. The ARCO® project team and the author's supervision engineers successfully cope with this task. The customer (investor) has set the task of completing the construction work and transferring the production capacities to pilot operation in May 2025. The plant construction work is generally on schedule.
Period November - December 2024