SEZ Krasnoyarsk Technological Valley. Results of the 2024 construction season. The final phase of construction of the first stage of the machine-building enterprise JSC Spetstekhnomash.

General construction works at the facility of the resident JSC Spetstekhnomash have been completed in general. The facility has been connected to external networks and communications. Commissioning works and bringing the engineering systems to operating modes are underway. Installation works have been carried out to install cranes on crane runways. The technical customer - ARCO is holding events with regulatory authorities and energy supply organizations to check the compliance of the work performed at the facility with the issued Technical Conditions. Construction is being carried out in accordance with the Schedule.

Period November - December 2024