General construction works at the facility of the resident LLC Henkon Siberia are generally completed. The facility has been connected to external networks and communications. Commissioning works and the engineering systems are being brought into operation. Installation works have been carried out to install the crane on the crane runways. The technical customer - ARCO is holding events with the regulatory authorities and energy supply organizations to check the compliance of the work performed at the facility with the issued Technical Conditions. Finishing works are being completed in accordance with the design project. Construction is being carried out in accordance with the Schedule.

Period November - December 2024